"PROJECT BROWN" HOUSE
History, Issues, Goals, Plan, Cost
THE PLAN
SURVEY & CLEAN PROPERTY
-
Dig Safe. Utility identification
-
Mark limits of excavation; prep edge of garage.
-
Remove Interior contents, including utilities, cut bushes, clean general surroundings.
ENGAGE GEN. CONTRACTOR
-
GC files for permit with Town of Northfield
-
GC provides plan details as required by town.
-
GC verifies assumptions about hazardous materials.
SCHEDULE A DATE
GC arranges the excavator transported to site.
GC arranges a disposal company for 4-5 40 yard dumpsters capable of 10 tons each.
GC arranges clean fill material for cellar hole.
Day 1: house is down, Day 2: debris is gone, cellar is filled, Day 3 is cleanup and loam seed.
- PROJECT COST -
$12,500
-
If you have specific detailed questions about the plan as presented, then please send an email directly to board member David Peters at petersfam@gmail.com. Please include "Camp Northfield Brown House" in subject line.
-
Volunteers needed for general labor help on all three days, especially Day 3.
-
If you would like to donate to the cost of the project or volunteer for some of the labor, then please contact Director Thomas Jackson at the camp office.
-
Thank you for your love, prayers, and volunteer support of Camp Northfield